Lean Enterprise Institute Logo
  • Contact Us
  • Newsletter Signup
  • Cart (78)
  • Account
  • Search
Lean Enterprise Institute Logo
  • Explore Lean
        • What is Lean?
        • The Lean Transformation Framework
        • A Brief History of Lean
        • Lexicon Terms
        • Topics to explore
          • Operations
          • Lean Product & Process Development
          • Administration & Support
          • Problem-Solving
          • Coaching
          • Executive Leadership
          • Line Management
  • The Lean Post
        • Subscribe to see exclusive content
          • Subscribe
        • Featured posts
          What is the difference between standard work and procedures?

          Lean Product and Process Development at Scale:...

          craftsmanship

          Pursuing Perfection: Craftsmanship in Product Development

          • See all Posts
  • Events & Courses
        • Forms and Templates
        • Featured learning
          • The Future of People at Work Symposium 

            July 18, 2024 | Detroit, Michigan

          • Hoshin Kanri

            September 06, 2024 | Coach-Led Online Course

          • Lean Warehousing and Distribution Operations

            September 11, 2024 | Plant City, Florida and Gainesville, Florida

          • Key Concepts of Lean Management

            September 16, 2024 | Coach-Led Online Course

          • See all Events
  • Training & Consulting for Organizations​
        • Interested in exploring a partnership with us?
          • Schedule a Call
        • Getting Started
        • Leadership Development
        • Custom Training
        • Enterprise Transformation​
  • Store
        • Book Ordering Information
        • Shopping Cart
        • Featured books
          Managing to Learn: Using the A3 management process

          Managing to Learn: Using the A3 management process

          A3 Getting Started Guide 2

          A3 Getting Started Guide

          • See all Books
  • About Us
        • Our people
          • Senior Advisors and Staff
          • Faculty
          • Board of Directors
        • Contact Us
        • Lean Global Network
        • Press Releases
        • In the News
        • Careers
        • About us

The Lean Post / Articles / What is the difference between standard work and procedures?

Article graphic image with repeating icons

Operations

What is the difference between standard work and procedures?

By Michael Ballé

December 28, 2015

Dear Gemba Coach: What is the difference between standard work and procedures?

FacebookTweetLinkedInPrintComment

Dear Gemba Coach,

What is the difference between standard work and procedures?

(During The Way to Lean, a free webinar on the “lean trilogy” approach to deeply understanding and applying kaizen daily, we received the above question plus dozens more that we didn’t answer before running out of time. Presenter Michael Ballé will answer them, including the response below, in the Gemba Coach column he writes for LEI. -Ed.)

Same – but different. This is one of these tricky areas where both things might look the same but their intent (and therefore use) is really different. Let’s see if we can untangle this.

Have you ever sat on an airplane next to an emergency exit? The flight attendant probably came to you to ask you whether you speak English and then:

  1. Place your belongings in the overhead compartment for take-off and landing.
  2. Read the safety brochure to familiarize yourself with the operation of the emergency door.
  3. In case of an emergency wait for airline staff’s direction and then turn lever one and lever two to open the door.
  4. Do NOT do so unless expressly directed by airline staff.
  5. Read the safety card again to see how the doors open.

Or something similar to that. If you’re anything like me at this point, you’re thinking that thankfully chances of having to open this door are ridiculously small because if you ever had to do it, you’d be in bad, bad trouble. The procedure is perfectly clear but not much use in a real situation.

To my mind, the main difference between a procedure and standard work is:

  • A procedure tells you what to do in a given situation.
  • Standard work tells you what you need to know to get the job done right first time.

Three Elements of Standard Work

Procedures are written by experts. They assume that if you just would stop thinking about it and follow the procedure step by step, the right process will guarantee the right outcome. This is of course much better than no procedure at all, but not much help when you hit a snag.

What about standard work? In his book on The Toyota Production System, Ohno describes standard work as a special kind of procedure that lists three core elements which had been used by Toyota since before WWII in loom manufacturing:

  1. Cycle time
  2. Work sequence
  3. Standard inventory

Ohno is assuming many things, such as the fact that all parts are assumed good and so on, but we can see that this differs from a procedure (as in “a series of actions conducted in a certain order or manner”) in important ways:

First, there’s a criteria for success: the work must be done correctly in a certain amount of time. This is very important because it states the difference between doing a good job or a bad job (rework, for instance, will lengthen the cycle time and be revealed).

Second it focuses on work sequence, not actions or activities. This is not nitpicking on words, but very specific. “Open the door” is a high-level instruction typically found in a procedure, whereas “turn lever A from clockwise with left hand and then turn lever B counter-clockwise with right hand” would be closer to standard work. Standard work is about the work itself.

Third, standard work specifies what you need at hand to get the job done (and what you don’t need in the case of having more inventory than immediately needed), which looks to the conditions you need to be in in order to do the work properly.

Focusing on the Outcome

To look at standard work in a broader sense we need to place it back in the context of just-in-time and jidoka. In order to keep up with takt time, the work must take place within a target cycle time and with minimum inventory, and in order to build in quality:

  • The necessary conditions to produce good quality must be known and controlled in the process
  • Clear judgment criteria must allow employees to make judgments about their own quality with confidence.

Standard work should cover:

  1. The job’s objectives from customers’ expectations perspective.
  2. The break-down into work elements, in manageable steps.
  3. The necessary conditions in terms of components, equipment, tools, capability and other inputs.
  4. Constant clarification of judgment criteria to make confident decisions about work completion (probably involving documentation and training by supervisor).
  5. On-going confirmation, instruction, and improvement.

Standard work goes beyond procedures in terms of focusing on the outcome of the job, the impact doing the job this way or that way has on safety, quality, cycle-time and lead-time and is expressed at a much greater level of detail about work, to the point where it touches the basic skills needed to carry out successfully the work at each step of the job.

Break the Standard

In practice, standard work starts where the procedure ends. Standard work is the result of the effort the supervisor puts into mastering the procedure (usually written by engineering or another expert department) and turning it into specific work habits to do the job right and on time confidently, every time. Beyond standard work, standardized work actually describes the very steps (eye movement, hand movement, feet movement) one can follow to do the job with the minimum waste.

The supervisor’s aim is to have eight hours of standardized work for every employee in her team. The team leader’s aim is to “break” the standard by suggesting with team members new, better ways of doing the job – and hence kaizen. Without standard work, it’s very difficult to see what to kaizen. Without kaizen, standard work soon falls into disuses and reverts to … procedure.

In the end, the difference lies in the intention of the procedure. Lean’s arrow is clear and simple: is management’s intent to make work easier for employees so they can succeed at their jobs and for customers? Or is it about bringing back control of what people do towards more management input and decisions? Are we getting closer to the final process of work and customer satisfaction? Or back to management meetings and action plans. Standard work’s main purpose is to turn procedures into actionable knowledge to make it easier for each employee to succeed for their customers and in their job.

FacebookTweetLinkedInPrintComment

Written by:

Michael Ballé

About Michael Ballé

Michael Ballé is co-author of The Gold Mine, a best-selling business novel of lean turnaround, and recently The Lean Manager, a novel of lean transformation, both published by the Lean Enterprise Institute. For the past 25 years, he has studied lean transformation and helped companies develop a lean culture. He is…

Read more about Michael Ballé

Leave a Comment Cancel reply

Your email address will not be published. Required fields are marked *

Related

A digitized brain exploding into vectors and jumbled computer code.

Operations

A New Era of Jidoka: How ChatGPT Could Alter the Relationship between Machines, Humans, and their Minds

Article by Matthew Savas

improvement kata coaching kata model 2

Operations

The Fundamentals of Improvement and Coaching Kata

Article by Lean Leaper

sensei back belt close up

Operations

Ask Art: Why is a Lean Sensei Necessary?

Article by Art Byrne

Related books

The Power of Process book cover

The Power of Process – A Story of Innovative Lean Process Development

by Eric Ethington and Matt Zayko

The Gold Mine (Audio CD)

The Gold Mine (Audio CD)

by Freddy Ballé and Michael Ballé

Related events

September 11, 2024 | Plant City, Florida and Gainesville, Florida

Lean Warehousing and Distribution Operations

Learn more

September 26, 2024 | Morgantown, PA or Remond, WA

Building a Lean Operating and Management System 

Learn more

Explore topics

Operations graphic icon Operations
Line Management graphic icon Line Management
Coaching graphic icon Coaching

Subscribe to get the very best of lean thinking delivered right to your inbox

Subscribe
  • Privacy Policy
  • Sitemap
  • LinkedIn
  • Twitter
  • YouTube
  • Instagram
  • Facebook

©Copyright 2000-2024 Lean Enterprise Institute, Inc. All rights reserved.
Lean Enterprise Institute, the leaper image, and stick figure are registered trademarks of Lean Enterprise Institute, Inc.

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Learn More. ACCEPT
Privacy & Cookies Policy

Privacy Overview

This website uses cookies to improve your experience while you navigate through the website. Out of these cookies, the cookies that are categorized as necessary are stored on your browser as they are essential for the working of basic functionalities of the website. We also use third-party cookies that help us analyze and understand how you use this website. These cookies will be stored in your browser only with your consent. You also have the option to opt-out of these cookies. But opting out of some of these cookies may have an effect on your browsing experience.
Necessary
Always Enabled
Necessary cookies are absolutely essential for the website to function properly. This category only includes cookies that ensures basic functionalities and security features of the website. These cookies do not store any personal information.
Non-necessary
Any cookies that may not be particularly necessary for the website to function and is used specifically to collect user personal data via analytics, ads, other embedded contents are termed as non-necessary cookies. It is mandatory to procure user consent prior to running these cookies on your website.
SAVE & ACCEPT